A product passes through three stages with yields of 95%, 98% and 97%. What is the rolled throughput yield?

  1. 96.67%
  2. 90.00%
  3. 95.00%
  4. 90.31%

Answer

D. 90.31%

Solution

RTY = 0.95 × 0.98 × 0.97 = 90.31%.

More Engineering Management questions

  1. A process produced 1500 units, each with 10 opportunities for a defect, and 45 defects were found. What is the DPMO?
  2. A p-chart uses samples of 100 items, and the average fraction defective is 0.04. What is the upper control limit?
  3. For an x chart with subgroups of 5, the grand mean is 50.0 and the average range is 4.0. What are the control limits? (A2 = 0.577)
  4. A process with specification limits of 9.4 and 10.6 mm has a mean of 10.2 mm and a standard deviation of 0.15 mm. What is its Cpk?
  5. A process has specification limits of 9.4 mm and 10.6 mm and a standard deviation of 0.15 mm. What is its process capability index Cp?
  6. A machine breaks down 3 times a month, each time stopping a 50-worker line for 8 hours. How many labor-hours are lost per month?
  7. An equipment investment of ₱500,000 yields net annual savings of ₱180,000. What is its simple payback period?
  8. Project A yields ₱500,000 profit with 60% probability or a ₱200,000 loss with 40% probability. Project B yields ₱300,000 (60%) or ₱50,000…
  9. Maximize Z = 2x + 5y subject to x + y ≤ 4, x + 3y ≤ 6, x ≥ 0, y ≥ 0. What is the maximum value of Z?
  10. Maximize Z = 3x + 2y subject to x + y ≤ 4, x + 3y ≤ 6, x ≥ 0, y ≥ 0. What is the maximum value of Z?

All Engineering Management Reviewer questions