Engineering Board Exam Reviewer · Engineering Management · medium

A worker's observed time for a task is 1.8 minutes, and the worker is rated at 110% performance. What is the normal time?

  1. 1.98 minutes
  2. 1.64 minutes
  3. 1.80 minutes
  4. 1.62 minutes

Answer

A. 1.98 minutes

Solution

Normal time = observed time × rating = 1.8(1.10) = 1.98 minutes.

More Engineering Management questions

  1. A job has a normal time of 2.0 minutes. With an allowance of 15%, what is the standard time? (standard time = normal time × (1 + allowance))
  2. A worker earns ₱120 per hour and works 46 hours in a week. Overtime beyond 40 hours is paid at 125% of the regular rate. What is the gross…
  3. A department of 50 employees had 60 person-days of absence in a month with 22 working days. What is the absenteeism rate?
  4. A company with 200 employees had 10 employees leave during the year. What is its annual employee turnover rate?
  5. A machine has an MTBF of 500 hours and a mean time to repair (MTTR) of 20 hours. What is its availability?
  6. A machine operated 2000 hours and failed 4 times. What is its mean time between failures (MTBF)?
  7. Two identical components, each with a reliability of 0.90, are connected in parallel (redundancy). What is the system reliability?
  8. A system has three components in series, each with a reliability of 0.95. What is the system reliability?
  9. A product passes through three stages with yields of 95%, 98% and 97%. What is the rolled throughput yield?
  10. A process produced 1500 units, each with 10 opportunities for a defect, and 45 defects were found. What is the DPMO?

All Engineering Management Reviewer questions