A worker's observed time for a task is 1.8 minutes, and the worker is rated at 110% performance. What is the normal time?
- 1.98 minutes
- 1.64 minutes
- 1.80 minutes
- 1.62 minutes
Answer
A. 1.98 minutes
Solution
Normal time = observed time × rating = 1.8(1.10) = 1.98 minutes.
More Engineering Management questions
- A job has a normal time of 2.0 minutes. With an allowance of 15%, what is the standard time? (standard time = normal time × (1 + allowance))
- A worker earns ₱120 per hour and works 46 hours in a week. Overtime beyond 40 hours is paid at 125% of the regular rate. What is the gross…
- A department of 50 employees had 60 person-days of absence in a month with 22 working days. What is the absenteeism rate?
- A company with 200 employees had 10 employees leave during the year. What is its annual employee turnover rate?
- A machine has an MTBF of 500 hours and a mean time to repair (MTTR) of 20 hours. What is its availability?
- A machine operated 2000 hours and failed 4 times. What is its mean time between failures (MTBF)?
- Two identical components, each with a reliability of 0.90, are connected in parallel (redundancy). What is the system reliability?
- A system has three components in series, each with a reliability of 0.95. What is the system reliability?
- A product passes through three stages with yields of 95%, 98% and 97%. What is the rolled throughput yield?
- A process produced 1500 units, each with 10 opportunities for a defect, and 45 defects were found. What is the DPMO?