The bar chart used for scheduling and tracking project activities over time was developed by:

  1. Frederick Taylor
  2. Walter Shewhart
  3. Henry Gantt
  4. Peter Drucker

Answer

C. Henry Gantt

Solution

The Gantt chart shows activities as horizontal bars on a time scale.

More Engineering Management questions

  1. The 'Father of Modern Management' (administrative management) who proposed the 14 principles of management is:
  2. The 'Father of Scientific Management' is:
  3. The management function that involves motivating, directing and communicating with people is:
  4. The management function that involves arranging tasks, people and resources into a structure is:
  5. The management function that involves setting objectives and deciding in advance how to achieve them is:
  6. Management is best defined as the process of:
  7. In an M/M/1 queue with arrival rate 8/hr and service rate 10/hr, what is the probability that the server is idle?
  8. Monthly demand is 2400 units with a standard time of 0.5 hour per unit. A month has 20 working days of 8 hours, and workers perform at 90%…
  9. In an M/M/1 queue with utilization 0.8, what is the probability that there are more than 2 customers in the system? (P(n > k) = k+1)
  10. Three jobs must be assigned to three machines, one job each. Costs (₱): Job 1 — M1: 9, M2: 2, M3: 7; Job 2 — M1: 6, M2: 4, M3: 3; Job 3 —…

All Engineering Management Reviewer questions