Engineering Board Exam Reviewer · Engineering Management · medium
An activity has optimistic and pessimistic times of 4 and 14 days. What is its variance?
- 1.67 days2
- 16.67 days2
- 2.78 days2
- 10.00 days2
Answer
C. 2.78 days2
Solution
2 = ((b - a)/6)2 = (10/6)2 = 2.78 days2.
More Engineering Management questions
- An activity has an optimistic time of 4 days, a most likely time of 6 days and a pessimistic time of 14 days. What is its expected time…
- Maintenance performed at scheduled intervals to prevent failures is called:
- A performance appraisal that gathers feedback from supervisors, peers, subordinates and customers is called a:
- A written statement of the duties and responsibilities of a job is called a:
- The value of the best alternative forgone when making a decision is the:
- A cost that has already been incurred and cannot be recovered is a:
- Costs that change in direct proportion to the level of production are called:
- Costs that do not change with the level of production in the short run are called:
- The economic order quantity (EOQ) model determines the order size that minimizes:
- Productivity is defined as the ratio of: