Engineering Board Exam Reviewer · Engineering Management · hard

A project has BAC = ₱2,000,000, AC to date = ₱450,000 and CPI = 0.80. What is the estimate to complete (ETC) if cost performance continues?

  1. ₱1,550,000
  2. ₱2,500,000
  3. ₱1,600,000
  4. ₱2,050,000

Answer

D. ₱2,050,000

Solution

EAC = 2,000,000/0.80 = ₱2,500,000. ETC = EAC - AC = 2,500,000 - 450,000 = ₱2,050,000.

More Engineering Management questions

  1. A project has a budget at completion (BAC) of ₱2,000,000 and a current CPI of 0.80. Assuming the cost performance continues, what is the…
  2. In Maslow's hierarchy, job security and safe working conditions satisfy which level of need?
  3. Which of the following tends to ALLOW a wider span of control?
  4. The systems approach views an organization as:
  5. The contingency approach to management holds that:
  6. Herbert Simon's idea that decision makers choose the first satisfactory alternative rather than the optimal one is called:
  7. A mode of thinking in which group members suppress dissent to maintain harmony, leading to poor decisions, is called:
  8. The tendency of people to improve their performance simply because they are being observed is called the:
  9. Fayol's principle that promotes team spirit and unity among employees is:
  10. 'Management by exception' means that managers should:

All Engineering Management Reviewer questions