Vic can finish a job in 19 days and Nina in 14 days. They work together for 1 day(s), then Nina leaves. How many days in all does it take to finish the job?
- 8 2/33 days
- 16 9/14 days
- 17 9/14 days
- 16 1/2 days
Answer
C. 17 9/14 days
Solution
In 1 day(s) together they finish 33/266. Remaining 233/266 takes Vic 16 9/14 days. Total = 1 + 16 9/14 = 17 9/14 days.
More Word Problems questions
- Three consecutive odd integers are such that the sum of the first and the third is 98. What is the largest of the three?
- If students sit 2 to a bench, 10 students have no seat. If they sit 3 to a bench, 4 bench(es) are left empty. How many students are there?
- Ana can finish a job in 6 days, Tess in 10 days, and a third worker in 15 days. How long will the job take if all three work together?
- What is the smaller angle between the hour and minute hands of a clock at 10:10?
- A train 380 m long travels at 108 km/h. How long does it take to pass a lamp post?
- The sum of the digits of a two-digit number is 11. If the digits are reversed, the new number is 27 less than the original. What is the…
- The sum of the ages of Paolo and Bea is 44. 4 years ago, Paolo was 2 times as old as Bea. How old is Bea now?
- Kiko leaves a town driving at 60 km/h. 2 hour(s) later, Hazel leaves the same town on the same road at 70 km/h. How long after Hazel…
- Paolo can finish a job in 17 days and Ben in 8 days. They work together for 1 day(s), then Ben leaves. How many days in all does it take…
- A pipe can fill a tank in 3 hours, while a drain can empty it in 6 hours. If both are open, how long will it take to fill the empty tank?