Hazel can finish a job in 11 days and Ben in 14 days. They work together for 3 day(s), then Ben leaves. How many days in all does it take to finish the job?

  1. 6 4/25 days
  2. 8 9/14 days
  3. 5 9/14 days
  4. 12 1/2 days

Answer

B. 8 9/14 days

Solution

In 3 day(s) together they finish 75/154. Remaining 79/154 takes Hazel 5 9/14 days. Total = 3 + 5 9/14 = 8 9/14 days.

More Word Problems questions

  1. A pipe can fill a tank in 2 hours, while a drain can empty it in 3 hours. If both are open, how long will it take to fill the empty tank?
  2. Pia received ₱1,400 as allowance. She spent 3/5 of it on books and 20% of the remainder on food. How much was left?
  3. A delivery van traveled 190 km in 5 hours. Part of the trip was at 30 km/h and the rest at 50 km/h. How many hours did it travel at 30 km/h?
  4. If students sit 5 to a bench, 9 students have no seat. If they sit 6 to a bench, 1 bench(es) are left empty. How many students are there?
  5. What is the smaller angle between the hour and minute hands of a clock at 2:40?
  6. A train 100 m long travels at 90 km/h. How long does it take to completely cross a bridge 360 m long?
  7. ₱220,000 was invested, part at 5% and the rest at 10% simple annual interest. The total interest after one year was ₱12,000. How much was…
  8. How many liters of water must be added to 40 liters of a 90% alcohol solution to reduce it to 20% alcohol?
  9. Ella can finish a job in 13 days and Carlo in 18 days. They work together for 2 day(s), then Carlo leaves. How many days in all does it…
  10. Three consecutive odd integers are such that the sum of the first and the third is 166. What is the largest of the three?

All Word Problems questions