Liza can finish a job in 9 days and Rina in 16 days. They work together for 4 day(s), then Rina leaves. How many days in all does it take to finish the job?
- 6 3/4 days
- 5 19/25 days
- 2 3/4 days
- 12 1/2 days
Answer
A. 6 3/4 days
Solution
In 4 day(s) together they finish 25/36. Remaining 11/36 takes Liza 2 3/4 days. Total = 4 + 2 3/4 = 6 3/4 days.
More Word Problems questions
- A pipe can fill a tank in 10 hours, while a drain can empty it in 12 hours. If both are open, how long will it take to fill the empty tank?
- Three consecutive odd integers are such that the sum of the first and the third is 62. What is the largest of the three?
- Gino has 5 times as much money as Ella. If Gino gives Ella ₱5,200, they will have equal amounts. How much does Gino have?
- If students sit 5 to a bench, 7 students have no seat. If they sit 6 to a bench, 2 bench(es) are left empty. How many students are there?
- Pia can finish a job in 8 days, Vic in 12 days, and a third worker in 24 days. How long will the job take if all three work together?
- What is the smaller angle between the hour and minute hands of a clock at 12:20?
- A train 390 m long travels at 108 km/h. How long does it take to pass a lamp post?
- ₱110,000 was invested, part at 5% and the rest at 9% simple annual interest. The total interest after one year was ₱6,700. How much was…
- The sum of the ages of Joy and Tess is 24. 8 years ago, Joy was 3 times as old as Tess. How old is Tess now?
- How many liters of water must be added to 30 liters of a 90% alcohol solution to reduce it to 25% alcohol?