Civil Service Exam Reviewer · Ratio and Proportion · hard

7 workers can complete a job in 28 days. After working for 18 days, 5 workers leave. How many more days will the remaining workers need to finish the job?

  1. 10 days
  2. 80 days
  3. 53 days
  4. 35 days

Answer

D. 35 days

Solution

Total = 196 worker-days. Done in 18 days: 126. Remaining: 70. With 2 workers: 70 ÷ 2 = 35 days.

More Ratio and Proportion questions

  1. 6 carpenters can finish a job in 28 days. How many MORE carpenters are needed to finish it in 12 days?
  2. ₱44,770 is shared among A, B and C such that A : B = 5 : 2 and B : C = 5 : 1. How much does C receive?
  3. A box has red and blue balls in the ratio 5 : 7. After 11 red balls are removed, the ratio becomes 29 : 56. How many blue balls are in the…
  4. Ana and Tess share some money in the ratio 7 : 4. Ana receives ₱7,020 more than Tess. How much money was shared?
  5. 9 workers working 8 hours a day can finish a project in 10 days. How many days will 4 workers working 6 hours a day need to finish the…
  6. The ratio of the number of pupils to teachers in a school is 70 : 1. If there are 32 teachers, how many pupils must be added so that the…
  7. ₱10,670 is shared among A, B and C such that A : B = 1 : 2 and B : C = 4 : 5. How much does C receive?
  8. A gear with 70 teeth rotating at 300 rpm drives a gear with 35 teeth. How fast does the second gear rotate?
  9. Alloy X contains gold and copper in the ratio 1 : 4; alloy Y contains them in the ratio 1 : 5. If equal weights of X and Y are melted…
  10. The ratio of the number of pupils to teachers in a school is 90 : 1. If there are 16 teachers, how many pupils must be added so that the…

All Ratio and Proportion questions