Civil Service Exam Reviewer · Ratio and Proportion · hard

15 carpenters can finish a job in 30 days. How many MORE carpenters are needed to finish it in 9 days?

  1. 50
  2. 35
  3. 21
  4. 37

Answer

B. 35

Solution

Work = 15 × 30 = 450 carpenter-days. Needed = 450 ÷ 9 = 50. Additional = 50 − 15 = 35.

More Ratio and Proportion questions

  1. A box has red and blue balls in the ratio 7 : 4. After 2 red balls are removed, the ratio becomes 17 : 10. How many blue balls are in the…
  2. A gear with 28 teeth rotating at 160 rpm drives a gear with 35 teeth. How fast does the second gear rotate?
  3. Mila and Rina share some money in the ratio 8 : 1. Mila receives ₱5,250 more than Rina. How much money was shared?
  4. Alloy X contains gold and copper in the ratio 1 : 2; alloy Y contains them in the ratio 1 : 3. If equal weights of X and Y are melted…
  5. The ratio of the number of pupils to teachers in a school is 80 : 1. If there are 24 teachers, how many pupils must be added so that the…
  6. 8 workers can complete a job in 17 days. After working for 2 days, 3 workers leave. How many more days will the remaining workers need to…
  7. ₱15,750 is shared among A, B and C such that A : B = 1 : 4 and B : C = 1 : 5. How much does C receive?
  8. Two similar boxes have corresponding sides in the ratio 5 : 7. What is the ratio of their volumes?
  9. Alloy X contains gold and copper in the ratio 5 : 2; alloy Y contains them in the ratio 3 : 2. If equal weights of X and Y are melted…
  10. The present ages of a father and his son are in the ratio 5 : 4. 8 years ago, the ratio was 27 : 20. What is the son's present age?

All Ratio and Proportion questions