Civil Service Exam Reviewer · General Information · medium
What is required before a project with significant environmental impact can proceed, under the Philippine EIS System?
- An Environmental Compliance Certificate (ECC)
- A business permit only
- A tax clearance
- A zoning variance
Answer
A. An Environmental Compliance Certificate (ECC)
Solution
An ECC, issued after review of an Environmental Impact Statement, is required for environmentally critical projects.