Civil Service Exam Reviewer · General Information · medium

What is required before a project with significant environmental impact can proceed, under the Philippine EIS System?

  1. An Environmental Compliance Certificate (ECC)
  2. A business permit only
  3. A tax clearance
  4. A zoning variance

Answer

A. An Environmental Compliance Certificate (ECC)

Solution

An ECC, issued after review of an Environmental Impact Statement, is required for environmentally critical projects.

More General Information questions

  1. What government agency serves as the primary implementing agency for environmental laws in the Philippines?
  2. What is the short title of RA 7586?
  3. What is the short title of RA 10121?
  4. What is the short title of RA 9729?
  5. What is the short title of RA 8371?
  6. What is the short title of RA 7942?
  7. What is the short title of RA 9147?
  8. What is the short title of RA 9003?
  9. What is the short title of RA 9275?
  10. What is the short title of RA 8749?

All General Information Reviewer questions