Engineering Board Exam Reviewer · Work Problems · medium

A and B together can finish a job in 12 days. A alone can finish it in 20 days. How many days would B need to do the job alone?

  1. 8 days
  2. 32 days
  3. 30 days
  4. 15 days

Answer

C. 30 days

Solution

B's rate is 112- 120=5-3/60= 130 per day, so B needs 30 days.

More Work Problems questions

  1. A can paint a house in 6 days and B can paint it in 3 days. Working together, how many days will they take?
  2. Mr. Yayama Nin can wash his car in 15 minutes, while his son Reese Kid takes twice as long to do the same job. If they work together, how…
  3. Pipes X and Y can fill an empty tank in 6 and 3 hours respectively. Drain D can empty a full tank in 24 hours. How long will an empty tank…
  4. Bing can finish a job in 8 hours. Bong can do it in 5 hours. If Bing worked for 3 hours and then Bong was asked to help her finish it, how…
  5. Bing, Bong and Bang can mow a lawn in 3, 4 and 6 hours respectively. What fraction (as a percent) of the yard can they mow in 1 hour if…
  6. A and B can do a piece of work in 60 days, B and C in 35 days, and A and C in 30 days. Working together, how many days can all of them…
  7. If 15 students can build a railway prototype 108 m long in 6 days, what length of similar railway can be built by 25 students in 3 days?
  8. Twenty-eight students can finish a certain design project in sixty days. At the start of the sixteenth day, five students dropped the…
  9. Marlon, Kimbert and Meryl can mow the lawn in 4, 6 and 7 hours respectively. What fraction of the yard can they mow in 1 hour if they work…
  10. One pipe can fill a tank in 6 hours and another pipe can fill the same tank in 3 hours. A drain pipe can empty the tank in 24 hours. With…

All Work Problems questions