Engineering Board Exam Reviewer · Work Problems · hard

In a company, x can do a job 50% faster than y and 20% faster than z. If they work together, they can finish the job in 4 days. How many days will it take x to finish the job if he is to work alone?

  1. 18 days
  2. 10 days
  3. 12 days
  4. 16 days

Answer

B. 10 days

Solution

1/x=1.5≤ft(1/y ) and 1/x=1.2≤ft(1/z ), so 1/y=1/1.5x and 1/z=1/1.2x. Combining: 1/x+1/1.5x+1/1.2x=1/4, giving x=10 days.

More Work Problems questions

  1. Candle A and candle B of equal length are lighted at the same time and burn until candle A is twice as long as candle B. Candle A is…
  2. The average rate of production of a PCB is 1 unit for every 2 hours of work by two workers. How many PCBs can be produced in one month by…
  3. Mr. Yayama Nin can wash his car in 15 minutes, while his son Reese Kid takes twice as long to do the same job. If they work together, how…
  4. Pipes X and Y can fill an empty tank in 6 and 3 hours respectively. Drain D can empty a full tank in 24 hours. How long will an empty tank…
  5. Bing can finish a job in 8 hours. Bong can do it in 5 hours. If Bing worked for 3 hours and then Bong was asked to help her finish it, how…
  6. Bing, Bong and Bang can mow a lawn in 3, 4 and 6 hours respectively. What fraction (as a percent) of the yard can they mow in 1 hour if…
  7. A and B can do a piece of work in 60 days, B and C in 35 days, and A and C in 30 days. Working together, how many days can all of them…
  8. If 15 students can build a railway prototype 108 m long in 6 days, what length of similar railway can be built by 25 students in 3 days?
  9. Twenty-eight students can finish a certain design project in sixty days. At the start of the sixteenth day, five students dropped the…
  10. Marlon, Kimbert and Meryl can mow the lawn in 4, 6 and 7 hours respectively. What fraction of the yard can they mow in 1 hour if they work…

All Work Problems questions